电厂主蒸汽管水压堵阀焊接裂纹分析及改进措施

电厂 主蒸汽管 水压堵阀焊接裂纹 分析 改进措施

大型火力发电厂主蒸汽管水压堵阀焊接裂纹分析及改进措施

林华 张明珠

(1.广西壮族自治区特种设备监督检验院 广西 南宁 530022; 2.国投钦州发电有限公司 广西 钦州 535008)

摘要:本文针对国投钦州发电有限公司#1锅炉主蒸汽管水压堵阀更换过程产生的焊接裂纹进行原因分析,并采取了相应的改进措施,最终解决了水压堵阀焊接裂纹技术难题,对水压堵阀现场施工工艺的编制具有参考作用。 关键词:堵阀; 焊接裂纹; 工艺措施

1

2

Weld crack analysis and improvement measures of main steampipe’s

pressure control valve in Large Thermal Power Plant

Lin hua1 Zhang Ming-zhu2

(1、Guangxi Zhuang Special Equipment Supervision and Inspection Institute GuangXi NanNing

530022; 2、SDIC Qinzhou Electric power.Ltd GuangXi QinZhou 535008)

Abstract: The paper studys on the reasons of weld crack, which has been in the process of replacement main steam pressure control valve of the No.1 boiler for SDIC Qinzhou Electric power.Ltd, and relevant improvement measures have been adopted, the technical problem of weld crack in the pressure control valve was setlled finally, the results contribute to establishment of pressure control valve’s constructing technology on the spot.

Key words: control valve; weld crack; technological measure

国投钦州发电有限公司一期工程建设两台60万千瓦超临界燃煤发电机组,其锅炉为东方锅炉(集团)股份有限公司生产的超临界参数变压直流炉,型号为DG1900/25.4-Ⅱ2型,一次再热、单炉膛、尾部双烟道、采用挡板调节再热汽温、平衡通风、露天布置、固态排渣、全钢构架、全悬吊结构Π型锅炉。1号机组于2007年7月5日顺利通过168小时运行,2008年3月4日主汽管道水压堵阀由于存在贯穿性缺陷在运行过程发生蒸汽漏泄,3月12日凌晨#1炉停炉,根据东方锅炉厂家建议,将漏泄堵阀更换为新堵阀(新堵阀由锅炉厂提供),堵

阀更换工作由山东xx公司负责实施,施工单位将旧堵阀切割下来,并对主蒸汽管道按要求加工坡口,然后与新的堵阀对口施焊,堵阀炉后侧焊口在焊到50mm厚度时,其焊缝两侧热影响区出现裂纹,将焊缝纵向切开后,发现裂纹已经延伸到根部,整个焊接工作被迫停止。本文通过对堵阀焊接裂纹分析研究,并提出堵阀焊接改进措施,取得良好的效果,克服了水压堵阀焊接裂纹技术难题。 1 堵阀焊接裂纹状况

堵阀及主蒸汽管道坡口加工如图1

[1~2]