1 目的 Purpose

规定设备和设施的清领、使用、维修、保管的管理,以确保设备、设施能满足最终产品质量的要求。

To specify management of drawing, use, repair and keeping of equipment and facilities to ensure that equipment and facilities are able to meet the quality requirements of final product.

2 适用范围Applicable scope

本程序适用于公司所有与产品质量有关的设施和设备的管理。

The procedure is applicable to management of all facilities and equipment related to product quality of the Company.

3 职责 Responsibility

3.1 总经理负责重大设施、设备(价格在1万元以上)配置申请的批准。

General manger is responsible for approval of application for allocation of important facilities and equipment (at the price of over RMB 10,000).

3.2 生产部负责生产设备的申请、使用、维修和报废过程的统筹管理:负责厂房、仓库及其设施的管理。Production Department is responsible for overall management of application, use, repair and discard processes of production equipment and responsible for management of workshop, warehouse and their facilities.

3.3 技术部负责生产设备的验收和重大设备的调试。

Technology Department is responsible for acceptance of production equipment and debugging of important equipment.

3.4 采购负责普通设备、设施的采购、重大设备设施(起毛机,定型机等)的采购应联络技术部和厂长参与。

Purchasing Department is responsible for purchasing of common equipment and facilities and Technology Department and factory manager shall be contacted to participate in purchasing of important equipment and facilities ( raising machine, shaping machine etc.)

3.5 使用单位负责设施、设备的使用管理和日常保养工作。

Use units are responsible for management of use of facilities and equipment and daily maintenance work.

4 作业程序Work procedure

4.1 设施配置与管理Allocation and managemetn of facilities

4.1.1 设施配置Allocation of facilities

a) 厂房的扩建、运输车辆、重大设备设施的购买有董事会决定。

Expansion of workshop and purchase of transportation vehicle and important facilities and equipment shall be decided by the board of directors.

b) 一般生产性设施,由使用部门填写设施设备配置申请表,交动力部门决定自制或外购意见,并落实完成时间,最后交厂长批准(如价格在1万元以上,还需要董事会批准)。 In the case of general production facilities, use department shall fill out application for allocation of facilities and equipment, submit to Dynamic Department to decide self manufacturing or outsourcing, and decide time of completion, and finally submit to factory director for approval (in case the price is over RMB 10,000, the application shall be submitted to the board of directors for approval).