● ___(75)___ is the process of obtaining the stakeholders' formal acceptance of the completed

project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

(75) A.project acceptance B.scope verification

C.scope definition D.WBS Creation

信息系统项目管理师2005年下半年

● __(66)__ means that every project has a definite beginning and a definite end.

(66)A.Project phase B.Unique C.Temporary D.Closure

● The __(67)__ defines the phases that connect the beginning of a project to its end.

(67)A.schedule B.project life cycle C.temporary D.milestone

● __(68)__ are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.

(68) A.Project managers B.Project team members

C.Sponsors D.Project stakeholders

● The __(69)__ Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

(69)A.Planning B.Executing C.Monitoring and Controlling D.Closing

● The __(70)__ provides the project manager with the authority to apply organizational

resources to project activities.

(70) A.project management plan B.contract

C.project human resource plan D.project charter

● The __(71)__ describes, in detail, the project's deliverables and the work required to create those deliverables.

(71) A.project scope statement B.project requirement

C.project charter D.product specification

● The process of __(72)__ schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

(72)A.estimating B.defining C.planning D.sequencing

● PDM includes four types of dependencies or precedence relationships: ... __(73)__. The

completion of the successor activity depends upon the initiation of the predecessor activity.

(73) A.Finish-to-Start B.Finish-to-Finish

C.Start-to-Start D.Start-to-Finish